Page 19 - Capability Statement
P. 19

Western Power HQ



           Western Power engaged Addelec to install, supply
           and maintain electric vehicle charging stations
           across three locations - Murrary Street, Forrestfield
           and Albany.

           The project included:

           • Installation and supply of 15 electric vehicle
            chargers and a load management system at their
            Murrary Street HQ
           • Installation and supply of 22 dual socket chargers
            and a load management system at their
            Forrestfield Depot
           • Installation and supply of 5 dual socket chargers
            and dedicated load management at their Albany
            depot
















           Cloud Carrier Data Centre


           Recently, Addelec began a comprehensive project
           for a client, focusing on the full electrical design and
           installation for a major data centre in Australia.

           The project included:

           • Engineering and designing the high-voltage (HV)
            network
           • Provision and installation of HV cables
           • Equipping the site with HV switchgear
           • Setting up comprehensive battery systems
           • Designing and implementing earthing systems
           • Installing and integrating the substation
            automation network
           • Performing a detailed protection study
            for the HV setup
           • Comprehensive project management services
           • Commissioning, including HV switchgear,
            transformers, battery systems, and substation
            automation components









                                                                                              Addelec Capability Statement | 18
   14   15   16   17   18   19   20   21   22   23   24